Court of Appeal closes Land Compensation Act loophole

 

23| 08 | 11

Neil Stockdale


A recent Court of Appeal decision closes a Land Compensation Act (1973) loophole which previously made it difficult for landowners to claim compensation for property depreciation which was caused by the construction of new public highways and roads constructed by house building developers.

 

Land compensation Act claims for compensation

The Court of Appeal in the case 'Thomas & Others v. Bridgend County Borough Council [2011] EWCA Civ 862' was concerned with claims for compensation under Part 1 of the Land Compensation Act for depreciation caused by noise and other nuisance from the newly constructed Hendre Relief Road. Previously certain rules under the Land Compensation Act (1973) operated unfairly and barred property depreciation claims for compensation.

 

Property depreciation resulting from new highway development

The problem for the landowner claimants in this case was that the Hendre Relief Road opened on 9th July 2002 but the highway did not become maintainable at public expense until 29th June 2006, almost four years later.  Any claims for property depreciation were therefore effectively barred from proceeding under Section 19(3) of the Land Compensation Act 1973 which states that claims cannot be made against a highway authority if that highway does not become maintainable at public expense within three years of opening.

 

The road itself had been constructed pursuant to an agreement between the highway authority and Redrow Homes, who under the terms of the agreement provided an indemnity to the highway authority in relation to claims under Part 1 of the Land Compensation Act.

 

Developer delays in bringing new roads up to highway authority adoption standards

The delay in the adoption of the new road and public highway, as being maintainable at public expense, was as a result of the developer failing to complete minor works to bring the road up to the required highway authority council adoption standard. 

In this case the Court of Appeal recoginsed that the developer, Redrow Homes, clearly stood to benefit from its own delay in bringing the road up to standard. Such a delay, which resulted in adoption being beyond three years of the road opening, would therefore prevent the landowner claimants’ putting in any claims for compensation for depreciation for which they would otherwise be liable.

 

There was no direct evidence in the case that the delay was motivated by a deliberate intention to avoid the compensation claims. However, the Court of Appeal noted that the practical effect of the arrangements was remarkable given that once the new road was opened there was little commercial incentive for the developers to hasten progress towards adoption. Though it appeared that Redrow Homes had good reasons to delay it until the expiry of the three year period for claims under Section 19(3).

 

Breach of landowner convention rights within Land Compensation Act

The Court of Appeal considered the relevant statutory background and the claimants’ argument that the provision was in breach of the claimants’ convention rights under Article 1 (right to peaceful enjoyment of possessions) and Article 6 (the right to a fair trial). The Court of Appeal rejected the claimants' submissions in relation to Article 6 but found that the provision was in breach of Article 1 and ruled that the claimants could proceed for making a compensation claim.

The Court Of Appeal judge, Lord Justice Carmworth, described the operation of the provision in the current circumstances as "truly bizarre". He recognised that the existing provision as outlined in the Act served to prejudice the diligent road builder who completed the project on time but reward the inefficient road builder who would be able to evade liability altogether.

 

The Court of Appeal was able to close the loophole by using powers under Section 3 of the Human Rights Act. Thus, accepting that these powers were sufficiently wide to enable the Court to re-interpret Section 19(3) of the Act. 

 

In this case the Court of Appeal fell short of providing a formal declaration as to the words to be read into the Section, but indicated that a qualification could be added to the relevant Section of the Land Compensation Act to provide that, “claims cannot proceed unless the highways becomes maintainable within three years, unless under an agreement made by the highway authority before the relevant date, the highway should reasonably have become so maintainable within that period".

 

Future implications for property developers constructing new highways

This case obviously has significant implications for councils and developers involved in the construction of public highways and wider implications in terms of the Court of Appeal's approach to the rights enshrined in Article 1 and the use of Section 3 of the Human Rights Act to interpret legislation.
Design by Brand 68 | Development by Fusionworkshop | SEO by Pinnacle Internet Marketing